Warburtons Bakery installs1.252 MWpRooftop Solar PVat their Wednesbury site
Warburtons Wednesbury bakery operates around the clock, with a substantial and continuous electrical demand driven by baking, cooling and packaging processes. To reduce grid import, cut carbon emissions and improve long term energy cost certainty, a 1.252 MWp solar PV system was designed and installed to work alongside the site’s existing 1 MW combined heat and power (CHP) plant.
Food Industry Heritage
Noble Green Energy is the renewable energy arm of the Noble Foods Group, one of the UK’s largest food producers and a supplier of eggs under the Royal Warrant. Noble Foods operates BRC-certified food manufacturing sites of its own, so the Noble Green Energy team arrives with a first-hand understanding of the hygiene protocols, foreign body controls and production continuity requirements that food manufacturers work to every day. For a live bakery operating 24 hours a day, this shared culture allowed the project to proceed without disruption to food safety or production.
1.252
MWp
SYSTEM SIZE INSTALLED
1.11
GWh
generated per annum
Circa
4 Years
estimated payback period
Aims & Objectives
Design Approach
The system was built on the SolarEdge DC optimised architecture.
- Each pair of modules is connected to an S1000 power optimiser, providing module level maximum power point tracking, module level monitoring and SafeDC voltage shutdown.
- Sense Connect adds continuous thermal monitoring of connectors, detecting potential faults before they can develop into arc events – a key consideration for a food production facility where fire risk and business continuity are critical.
Integration with Existing CHP
A defining feature of this project is the coordination of the new solar array with the site’s existing 1 MW CHP plant. The building’s typical electrical load is in the region of 1.2 to 1.4 MW, a substantial proportion of which was already being generated on-site by the CHP, with the balance imported from the grid. The solar PV system was designed to target that remaining import. With the CHP and solar PV generating in parallel, grid import falls to around 100 kW during peak solar production, meaning over 90% of the site’s demand is met by on-site generation.
Looking ahead, there is an aspiration to prioritise the solar array as the leading generation source, allowing the cleaner, lower cost PV output to displace a share of the CHP’s contribution and further reduce both the site’s carbon footprint and its cost of energy. The control and metering arrangement ensures both generation assets operate within the site’s G100 export limitation, with real time monitoring of generation, import and CHP output.
Outcomes
-
System Specification:
- System size: 1.252 MWp
- Modules: 2,753 x Trina Solar TSM-455 Vertex S+
- Power optimisers: 1,395 x SolarEdge S1000, with SolarEdge Sense Connect
- Inverters: 8 x SolarEdge SE100K (100 kW)
-
Total Installed Capacity: 1.252 MWp
-
Estimated Annual Generation: 1.11 GWh per annum
-
Module level monitoring and fault detection across all panels
-
Enhanced fire safety through SafeDC and Sense Connect technology
-
Grid Offset: Over 90% of demand met by on-site generation
-
Reduced exposure to volatile grid electricity prices
-
Zero export compliance achieved through dual ENA registered systems, witness tested by NGED
-
Permanent rooflight mesh providing safe long-term access for maintenance of all roof plant
Challenges & Mitigation
Safe Roof Access and Bespoke Mounting Design
Working at height on a live production facility required careful planning. All building rooflights and skylights were covered with temporary netting for the duration of the works, allowing the installation team full roof access without the need for harnesses and enabling safe, efficient working across the entire roof area. The mounting frame was a bespoke design, developed to allow modules to be installed over the skylights where possible and maximising the usable roof area. On completion, the remaining exposed rooflights were fitted with a permanent mesh, providing safe access for all ongoing maintenance of the roof mounted plant.
Zero Export Compliance
The site’s connection agreement did not permit any power export to the grid network. Export limitation is managed by the SolarEdge G100 system. As the site is connected to the grid at 11 kV, secondary protection was required. This was provided by Juggle Energy’s J-Box, giving full control of the automatic disconnection devices. Both systems are ENA registered products and were witness tested by NGED engineers to confirm compliance with the connection agreement.
“…As part of the Noble Foods Group, we understand the demands of live food production environments, from hygiene controls to fire risk and business continuity. This was our second project with Warburtons, delivered through genuine collaboration and a health and safety culture shared by both organisations. Work is now underway on a third project of similar scale….”
Summary
Demonstrating integration with existing on-site generation
The Wednesbury installation demonstrates how a large rooftop solar array can be integrated with existing on-site generation to deliver near self-sufficient daytime operation for an energy intensive manufacturing site, without compromising grid compliance or operational safety. Noble Green Energy’s food industry heritage ensured the work was delivered to the standards a major food manufacturer expects, with production continuing uninterrupted throughout.



Ready to Empower Your Business?
Contact the friendly and experienced team at Noble Green Energy to discuss a solution for your business.
Watch our Case Study Video
Take a look at our case study below to see how we installed solar energy solutions at Warburtons Wednesbury.